Order your Garden Room Building
IN JUST A FEW STEPS
1.Introduction
Learn more about what Green Retreats has to offer:
Use our visualiser to customise your very own garden room to meet your specifications and budget.
Visit us at either our Buckinghamshire showroom, where we have 20 garden rooms in our indoor and outdoor environment or our Twickenham showroom with 4 buildings from our ranges.
Get a fast, no-obligation quote for your dream garden room—simple, quick, and tailored to your needs!
We offer a no obligation site survey and design consultation to check that your plot is suitable and to assist you in designing your perfect garden room.
Your garden room brochure allows you to browse our range of garden rooms in the comfort of your home.
2.BOOK AN INSTALLATION DATE
Whether you are in the speculative or advanced stages of planning your garden room, you can secure your date. A £300 deposit guarantees the date of your choice.
Once that is sorted you can decide on your building style and choices, or if this is already done you can sit back and relax until closer to the installation date.
3.FINALISE YOUR DESIGN
6 weeks prior to your installation date we will begin production of your garden room.
At this point a member of our customer care team will be in touch to confirm any final details as well as provide you with an electrical plan to confirm the placement of lights, switches, sockets and consumer unit. After this time, no further changes to your garden room or installation date can be made.
4.DELIVERY AND INSTALLATION
All Green Retreats garden rooms are delivered to you by our own fleet of trucks and installed by our highly trained staff. Delivery is included within 100 miles of our factory – HP18 0XB.
THE BASE/FOUNDATIONS
The base foundations for your garden room is completed normally 1 week before your installation date – giving time for the concrete to set. The base takes around half a day for our teams to create and test.
YOUR GARDEN ROOM:
Installation of your garden room takes between 2-5 days with the main structure being weather tight by the end of the first day. Plastering and painting options make the completion date for your building several weeks later.
Our
PAYMENT SCHEDULE
STEP 1
£300 Holding Deposit
Due: At any early stage of your planning
Your £300 holding deposit secures your installation date and locks in your quoted price for 1 year from the date the order is placed. It’s fully changeable and refundable up until 6 weeks before your installation date – giving you complete peace of mind while you finalise your plans.
STEP 2
60% BUILDING DEPOSIT
Due: 6 weeks before installation
We require confirmation of your building 6 weeks prior to installation. At this point, a 60% deposit is due, which secures your order and sends your building into production. This step ensures everything is ready and on track for your scheduled installation date. No further changes can be made after this payment has been taken.
STEP 3
REMAINING BALANCE
Due: 30% on final day of initial construction.
It typically takes 2–5 days to install your garden room. On the final day of this initial construction phase, we require 30% of the remaining balance. This payment confirms completion of the main building structure and allows us to proceed with the finishing touches such as electrics.
STEP 4
Final 10% of Remaining Balance
Due: On full building completion
After the main structure is installed, final works such as electrics, plastering, and any optional extras like air conditioning will be completed. Once these finishing touches are done, the remaining 10% balance is due. At this point, your 12-year guarantee is also activated, giving you complete peace of mind.